The First Wind Turbine

The First Wind Turbine at Cheyne Court Farm

Rye’s Own July Supplement 2008

The first of the Wind Farm turbines are up Each one towers 370 feet above the ground, that’s twice the height of the existing pylons

A Fact Sheet records that the development site extends to very nearly one and a half square miles in two parishes. The concrete foundations for the turbines are well over 100 foot deep and the total amount of earth moved filled over 46,000 (forty six thousand) lorries. Continue reading The First Wind Turbine

Rye Fights Back

Protest Rally at Postern Gate

Critics of Rye Town Council members had better beware. That is the message coming from many Councillors. They are fed up with being ruled by Rother District, East Sussex and other bodies such as the Primary Care Trust. Continue reading Rye Fights Back